India could add only 480 mw of
new capacity in January, a
sixth of the month’s target.
Unless the next two months
achieve a turnaround, the fourth
quarter could see a reversal of
improvement in the pace to 4,795
mw in the third quarter, from 2,870
mw in Q2 and 2,065 mw in Q1.
The performance has lifted the
total capacity commissioned
during the first 10 months of the
current fiscal to 10,211 mw-58
per cent of 17,748 mw planned
for the period. The projects commissioned
during January
included the 125-mw Barsingsar
Lignite TPP, Unit-2 of Neyveli
Lignite Corporation Ltd; 135-
mw Wardha Warora TPP, Unit-3
of Wardha Power Company Ltd
(KSK Energy Ventures Ltd); and
220-mw Kaiga Unit-4 of Nuclear
Power Corporation of India Ltd.
Cumulatively, the net capacity
addition in public utilities till January
in the ongoing 11th Plan
amounted to 28,873 mw, comprising
25,280 mw of thermal, 2,713
mw of hydro (renewable) and 880
mw of nuclear power.
Untitled Document
Power Sector Performance in 11th Plan |
|
2007-08 |
2008-09 |
2009-10 |
2010-11 (up to January) |
| Capacity addition (mw) |
9263 |
3454 |
9585 |
10211 |
| Generation ('000 GwH) |
704 |
724 |
772 |
669 |
| Power deficit (per cent) |
9.8 |
11 |
10.1 |
8.6 |
The renewable energy sources
(grid connected) including small
hydropower, biomass gas/power
and wind energy etc., whose
estimates are sourced from the
Ministry of New and Renewable
Energy, contributed 9,026 mw.
The addition to the stock of public
utilities exceeded 21,151 mw
in 10th Plan and 18,524 mw in
the 9th Plan. In fact, renewable
energy, a star performer, has surpassed
the achievements in the
earlier Plan by 50 per cent.
The total stock of installed generating
capacity at the end of January
worked out to 170,229 mw; of
which thermal power comprised
111,294 mw, large hydropower
37,367 mw, nuclear 4,780 mw, and
RE sources 16,787 mw. Grid-connected
captive generating capacity
contributed another 19,509 mw.
Power transmission: The
capacity addition of 28,031 ckm to
400kV transmission lines and
18,633 ckm to 220kV transmission
lines till January in the ongoing
11th Plan has exceeded their
respective additions during the
10th Plan. Likewise, the additions
in terms of MVA in 400kV and
220kV substations also surpassed
their 10th plan augmentation.
Growth in generation: Total
power generation including that
from the Bhutan joint venture
increased by a record 9.3 per cent
in January, against 4.3 per cent in
December, 3.4 per cent in November
and 8.3 per cent in October.
Before this, the growth rate in
power generation had collapsed
to around 1.6-1.7 per cent average
in August-September, from 3.9
per cent in June-July and 6.6 per
cent during April-May.
The cumulative increase in
power generation over April-January
2010-11 worked out to 5.04
per cent, which was still below 6.1
per cent in the corresponding
period of 2009-10. Plant load factor
for thermal plants (coal and lignite
based) which was up by 3.5
per cent was assessed at 73.7 per
cent during April-January 2010-
11, markedly lower than 76.7 per
cent in this period a year ago.
PLF for nuclear power improved
from 49 per cent to 61 per cent
between these periods due to better
availability of nuclear fuels.
Power deficit: The average
deficit worked out provisionally to
7.6 per cent in January, lower
compared to 8.2 per cent in
December, which had reversed
the declining trend of the past two
months that had brought down
the deficit to 6.5 per cent in
November. Deficit during the first
10 months of the current fiscal
worked out to 8.6 per cent, inferior
compared to 9.9 per cent in the
corresponding period a year ago,
and 11 per cent in this period two
years back. In fact, after running
higher till August, relative to yearago
levels, power deficit has tended
to be less severe than year-ago
levels in subsequent five months.
Cumulative peak demand level
deficit worked out to 11.1 per cent,
against 12.6 per cent in the same
period last year and 13.8 per cent
two years back. Lower power
shortage could be reflective of a
slowing economy as growth in
generation during the period was
lower than that a year ago.
Among the regions, Western
region faced 13.4 per cent average
deficit, much higher than the
average for the country; Northern
region faced 8.3 per cent deficit;
Southern region and the Eastern
region faced 5.2 per cent and 4.4
per cent deficit, respectively.
Among the states, Maharashtra,
the biggest power consumer state,
faced 17 per cent power deficit
during April-January 2010-11.
Madhya Pradesh saw 20 per cent
deficit and Uttar Pradesh 16 per
cent. In Southern region, Karnataka
faced 7.8 per cent. Andhra
Pradesh and Tamil Nadu saw
much lower deficit of 3.4 and 6.2
per cent shortage, respectively.