While the concept of independent
power producers has
been in existence for over
two decades, it the tariff-based ultra
mega power project series that is seen
as the biggest token of the PPP model
in the power generation side. The
UMPP endeavour involves the setting
up of around ten power projects based
on fuel-efficient supercritical technology.
The envisaged capacity of each
power plant is around 4,000 mw. The
UMPP endeavour is scheduled to
commission in the XII Plan (2012-17)
but some units (if not entire plants) are
envisaged to turn operational within
the ongoing Plan period itself.
So far, four UMPPs have been
awarded. These are Mundra
(Gujarat), Sasan (Madhya Pradesh),
Krishnapatnam (Andhra Pradesh)
and Tilaiya (Jharkhand). The remaining
six to seven are under various
stages of pre-bidding. At a recent
event in Mumbai, Union power minister
Sushilkumar Shinde expressed his
appreciation on the UMPP series but
admitted that there has been some
delay in awarding projects. He even
observed that setting up of power
plants of this magnitude has won India
admiration at the global level. However,
when asked about his view on the
fact that three out of the four projects
awarded have gone to the same
developer, he noted that the power
ministry has decided to limit the number
of UMPPs given to a single developer
to three. It may be mentioned that
the Sasan, Krishnapatnam and Tilaiya
UMPPs have been won by Anil
Ambani-controlled Reliance Power.
The Mundra project is being developed
by Tata Power Company.
The new directive, suggested by the
power minister, will ensure that private
sector participation does not concentrate
around the same entrepreneurial
group. Industry experts believe that
while tariff-based bidding ensures
technical and commercial efficiency, a
situation where same developers get
multiple projects increases the overall
project risk profile. It can therefore be
expected that the remaining UMPPs
will see a fresh set of developers. The
bidding for the four projects awarded
so far has witnessed healthy competition
from domestic and even international
players.
Impact of fuel costs: With effect
from January 5, 2011, all projects in the
power sector would be awarded
through the tariff-based bidding mechanism.
Hence, it is of paramount
importance for the developer to
ensure that the winning tariffs can be
sustained over the duration of the
power purchase agreement. With
respect to coal-fired power projectsthe
UMPP series being such-coal
availability and pricing play a very critical
role in keeping the tariffs sustainable.
Some of the UMPPs are based
on imported coal. Among the four
awarded, Mundra and Krishnapatnam
are such. It has so happened that
developers of these UMPPs had
entered into long-term agreements
with coal suppliers from Indonesia and
Australia, among others. The coal was
made available at much lower than
market rates, in view of the long tenure
of the fuel supply contract. However, in
a much unexpected move, the Indonesian
government recently directed that
no exports of coal would be allowed at
less-than market prices. This has jolted
developers like Tata Power and
Reliance Power who has finding it difficult
to sustain the winning tariff of their
respective UMPP. The Union power
ministry accepted the consequent difficulties
in store for private developers
and assured that India will negotiate with coal sourcing countries. It is also
understood that while the normal
power purchase agreements factor in
a general cost escalation clause,
future UMPPs will have a specific
clause with respect to price fluctuations
of imported coal. This being so,
the second round of bidding for the
Orissa UMPP has been delayed. In
the first round of bidding, over twenty
entities participated.
First UMPP soon: Tata Power
Company expects to commission
the first unit of its 5x800-mw supercritical
Mundra ultra mega power
project in Gujarat by March 2012.
The unit has already been synchronized
to grid following availability
of the power evacuation
facility in September last year. The
unit was delayed due to non-availability
of power transmission lines
on time. Work on the remaining
four units of the supercritical
Mundra power plant is progressing
well, a statement by Tata Power
observed. The 800-mw rated
power units of the Mundra project
will be the largest operational in
India, an industry observer noted.
Meanwhile, Reliance Power
expects to commission the first
unit of its 6x660-mw Sasan UMPP
in Madhya Pradesh during 2012-
13. Shanghai Electric Corporation
(SEC) is the main plant supplier on
whom the order was placed in July
2008. The order for balance of
plant works has also been placed.
According to latest reports available,
the boiler foundation of five
out of the six units has been constructed,
among much other
progress achieved. |