Home

Wednesday, June 19, 2013

Lead Story
News
Edit Page
PM Interview
New Projects
Orders & Contracts
Transport
Power
Special Feature:
India Infrastructure
Sister Concern
Archives

 
 

Is there a way out?



Strange as it seems, no amount of learning can cure stupidity, and higher education positively fortifies it
- Stephen Vizinczey, author

Official Permissions

In India setting up a mega project also means inviting mega problems. There are innumerable clearances one has to obtain and umpteen departments one has to run around. Even after taking all this trouble, project developer will not be sure whether he has complied with all the provisions of the land.
For setting up a thermal power plant, clearances have to be obtained by the project developer from as many as 10 different authorities besides getting investment clearances from financial institutions and public investment board in respect of projects taken up by PSUs. There are many instances where projects were delayed because clearances were not forthcoming in time. The situation will be even worse when a project involves more than one state.
p>Readers may mail their comments to editor@projectsmonitor.com

For example, Vindhyachal Stage III was delayed by more than four years only because necessary clearances regarding water commitment were made available by CWC/the ministry of water resources after four years from the date of applications. These clearances, including those from the ministry of environment and forest regarding site and environment should have been given within one year.
Vindhyachal Stage IIII project was taken up for commissioning by NTPC. Applications for obtaining water clearance/environmental clearance were submitted by NTPC in time. But it took an exceptionally long time of four years for obtaining water clearance from the Central Water Commission/ the ministry of water resources as water source was from an inter-state river basin where the concerned basin states -- Madhya Pradesh, Uttar Pradesh and Bihar -- did not arrive at consensus on water sharing.
There was a move to create a Special Purpose Vehicle with an objective to coordinate with the MOEF and the State Forest Departments. A draft Memorandum of Understanding between the ministry of power and the ministry of environment and forest towards this objective was prepared. However, this draft is pending with MOEF since September 20, 2001, with no further action being taken. This shows the lack of seriousness of the ministries to resolve issues.
The government has set itself an ambitious target of adding one lakh MW of additional power generation capacity by the end of 11th plan. Most of this will happen in the thermal sector. If the files move from one ministry to another at the same pace at which they have been doing for years, then we may not be able to achieve this target even in the next 50 years. A recent Standing Committee recommendation that a Central committee consisting of officials from the ministries of power, water resources and environment and forests and other related departments should be created to provide all clearances to the power projects in a time-bound manner should be given a favourable consideration.


[29 May 2006]



 

ICICI Lombard Insurance

Ceramics technologies

FRS Solutions 2008

Petro Tech 2009

Marcus sucessful Construction contracting

EA Water Expo 2008


  Home

Wednesday, June 19, 2013          Archives | About us | Contact us | Feedback | Advertise | Post Projects

Copyright (c) 2001 Economic Research India Limited
Disclaimer, Privacy Policy