11,404 mw till August
Dr. M.S. Kapadia
power capacity addition in 11th Five-Year Plan
A total of 11,404 mw of power capacity was commissioned till August in the 11th Five-Year Plan, comprising 8,472 mw of thermal capacity, 2,712 mw of hydro power
and 220 mw of nuclear power. With this and including around 12,195 mw from
renewables, the total generating capacity rose to 145,627 mw by the end of that
month.
Moreover, 64,432 mw is likely from planned projects under construction and
another 4,234 mw from additional projects, which takes the likely capacity
addition to around 77,070 mw over the plan period. Thermal power would
contribute 58,183 mw, hydro 15,507 mw and nuclear 3,380 mw.
The current fiscal is likely to see capacity addition of 7,530 mw, of which
2,141 mw was commissioned by August and 5,389 mw programmed to be operational in
next seven months.
The major projects that will see completion over September-March 2008-09
include:
u 450-mw Baglihar-I hydro
power plant of Jammu & Kashmir Power Development Corporation in J&K,
commissioned on October 10.
u 500-mw Kahalgaon-II
unit-7 thermal power plant of NTPC Ltd in Bihar.
u 752-mw Sugen Torrent
thermal power plant of Torrent Group in Gujarat.
u 445-mw Konaseema
thermal power plant of Oakwell in Andhra Pradesh.
u 464-mw Gautami thermal
plant of Gautami Power in Andhra Pradesh.
u RAPP units 5&6 in
Rajasthan (440 mw) and Kaiga unit 4 in Karnataka (220 mw) nuclear power plants
of NPCIL.
|
Status of 11th Plan Projects as of August
2008 (MW) |
|
|
Thermal |
Hydro |
Nuclear |
Total |
|
2007-08 (Comm) |
6,620 |
2,423 |
220 |
9,263 |
|
2008-09 |
|
|
|
|
|
Comm |
1,852 |
289 |
0 |
2,141 |
|
Yet to Comm |
3,921 |
808 |
660 |
5,389 |
|
2009-10 |
11,646 |
1,805 |
2,200 |
15,651 |
|
2010-11 |
16,572 |
1,741 |
500 |
18,813 |
|
2011-12 |
17,572 |
8,441 |
0 |
26,013 |
|
Total |
58,183 |
15,507 |
3,380 |
77,070 |
[October 20-26, 2008]
|