Project Name
|
Name
of the Promoter
|
Project
Cost (in crore)
|
Location
|
Project Details
|
Remarks
|
|
Delhi Metro
Rail Project
|
State
and
Central
Govts
|
8,100
|
Delhi
|
Implementation of mass rapid transit system project in
two phases. First phase involves an investment of Rs 8,100 crore
|
Contracts
for several packages have been awarded and work commenced. A few contracts are in
the process of finalisation. In March
2001, a consortium comprising Larsen & Toubro among four other companies has
bagged a Rs.1,650 crore contract for the construction of an underground corridor
between ISBT station to Central Secretariat. The entire project is expected to be
completed by March 2005.
|
|
Bhogibheel Rail-cum- Road
Project
|
Northeast Frontier Railway
|
1,800
|
Sisi and
Dibrugarh,
Assam
|
The project, included in
budget 1997-98, envisages the laying of 46.5- km of railway track and 29.5- km of
road. It also includes a 4.315-km Bogibheel rail-cum-road bridge
|
In September 2000, the scheme received
‘in-principle’ clearance of the Cabinet Committee on Economic Affairs (CCEA).
The detailed investigation and final location survey has been taken up by RITES. The project is expected to be completed in seven
years from the zero date.
|
|
Khurda Road-Bolangir SL Railway Line
|
South
Eastern Railway
|
700
|
Orissa
|
The project involves
construction of a new railway line from Khurda to Bolangir in Orissa
|
The work on the final
location survey is in progress. Tender for earthwork and minor bridge for first 2 km
on railway land have been finalised. Work is expected to commence once land is
handed over by state government.
|
|
Lumding-Silchar GC Railway Line
|
Northeast Frontier Railway
|
648
|
Assam
|
The project, which received Central government
approval in April 1996, aims to connect Lumding in Nagaon district with Silchar in Cachar district, Assam
|
Earthwork and bridges are in
progress between Lumding and Silchar in 90 km length (40 km from Lumding end and 50
km from Silchar end). 40 per cent of the eathwork in this section has been
completed. Out of the 138 minor bridges 50 has been completed. Work on the
Silchar-Jiribam gauge conversion is being carried out as a material modification of
this work.
|
|
Daitari-Bansapani SL Railway Line
|
South
Eastern Railway
|
585.12
|
Orissa
|
The project is being
implemented with private sector participation. The rail line is considered to be
vital in order to transport iron ore from the north-western parts of the state to
the coastal areas where the co-promoters of this project are proposing to set up
their respective steel plants
|
Most
of the land acquisition work is over. Earthwork and bridgework are in progress from
Banspani end. Out of 361 bridges works on 207 minor bridges have been completed and
on 24 major bridges have been taken up. The project is expected to be completed by
December 2003 subject to availability of resources.
|
|
Munirabad-
Mehboobna-gar Railway Line
|
South
Central Railway
|
438.96
|
Karnataka
-AP
|
The project involves the
construction of a 230-km new line between Munirabad and Mahabubnagar
|
In December 2000, foundation stone for the railway line
was laid. And a sum of Rs.5 crore is proposed in the budget of 2001-2002.
|
|
Haridaspur-Paradip SL Railway Line
|
South
Eastern Railway
|
301.63
|
Orissa
|
The proposed line would
facilitate the movement of mineral ores from Daitari, Sukinda and Kendujhar areas of
the state and also from the south of Bihar to Paradeep port
|
A total of 1,300 acres of
land in the districts of Jaipur,Kendrapura and Jagatsinghpur would be acquired. The
location of the railway track and stations along the NH-5 has also been finalised.
|
|
Guntakal-Renigunta Railway Line Electrif-
ication
|
South
Central Railway
|
270
|
Andhra
Pradesh
|
The project involves
electrification of the Guntakal-Renigunta line
|
Work is in progress and is
expected to be completed by March 2004.
|
|
Peddapalli-Karimnagar
-Nizamabad SL Railway Line
|
South
Central Railway
|
246.84
|
Andhra
Pradesh
|
Railway line
to be laid between Peddapalli in Karimnagar district of Andhra Pradesh
Nizamabad in Nizamabad district of AP
|
The 35
km line between Peddapalli and Karimnagar became operational in May 2000. Survey
work on the Karimnagar-Nizamabad section has been completed. As of February 2001,
work is in progress on the Karimnagar-Nizamabad section.
|
|
Harmuti-Itanagar Railway Line
|
Northeast Frontier Railway
|
156
|
Arunachal
Pradesh
and Assam
|
The
project received the Centre’s approval in February 1997
|
Work
is expected to be completed by December 2005
|