Mumbai Metropolitan Region Development Authority (MMRDA) has invited bids for works of Mumbai Metro Line 2B.

The scope of work includes design, manufacture, supply, installation, testing and commissioning of two 110 kV receiving substation including 110 kV, 33 kV & 25 kV cabling work, complete 25kV overhead catenary system along with switching station, 33 kV auxiliary power distribution system including 33/0.415 kV auxiliary sub-station (ASS) and complete SCADA system for Main Line and Depot of Mumbai Metro Line 2B.

The estimated cost of the project is Rs 443.37 crore with completion period of 36 months.