tunnelThe Mumbai Metro Rail Corporation (MMRC) has achieved 100 percent excavation on 13 of 26 underground stations on Mumbai Metro-3 corridor.

MMRC will complete excavation work for the remaining stations by May 2020.

Overall, MMRC has completed 87 percent excavation work. Moreover, 70 percent tunnelling work for 33.5 km underground corridor has also been completed.

The 13 stations include Cuffe Parade, Vidhan Bhavan, Churchgate, Hutatma Chowk, Chhatrapati Shivaji Maharaj Terminus, Science Museum, Siddhi Vinayak, MIDC, Marol Naka, Sahar Road, CSMIA Domestic, CSMIA International and Seepz.

Among the next 13 stations, MMRC has completed more than 80 percent excavation work in Worli, Dadar, Dharavi, BKC, Vidyanagari, and Santacruz.

The activities like construction of the station boxes, which is already underway, will take shape.