The physical and financial progress of Patna Metro Rail project is 1.6 percent and 2.79 percent respectively, till February 2022. 

The physical and financial progress of Patna Metro Rail project is 1.6 percent and 2.79 percent respectively, till February 2022. The physical and financial progress of Patna Metro Rail project is 1.6 percent and 2.79 percent respectively, till February 2022.

So far, Rs 615 crore has been spent on the construction work on the priority corridor between Malahi Pakri and Patliputra bus terminal. The sanctioned cost of the project is Rs 13,365 crore, in which the central share is Rs 1,840 crore.

A sum of Rs 262 crore has already been given to the state government. The state government’s share is Rs 5,908 crore including land acquisition, of which Rs 1,070 crore has been released.