train+tracksThe Maharashtra Rail Infrastructure Development Corporation has invited separate bids for works in Nagpur Division of South East Central Railway, Maharashtra.

The work involves construction of all civil works up to formation level from (-) ch 1.214 km to 30.00 km between Nagbhir to Bhiwapur section and from ch 30.00 km to 55.00 km between Bhiwapur to Umred section.

The scope of work includes construction of all civil works upto formation level including dismantling of the existing Narrow Gauge line, earthwork, blanketing, major & minor bridges road under bridges (RUB)/ limited height subway (LHS) retaining walls, drains, cross drainage works, relocation of the existing roads & utilities, providing & fixing of overhead equipment mast, etc and all chord lines, shunting, isolations/sand hump/cross overs etc in all the station yards in connection with Gauge Conversion work.

The estimated cost of the project between Nagbhir to Bhiwapur section is Rs 151.58 crore while between Bhiwapur to Umred section is Rs 155.6 crore.

The completion period for each project is 10 months.